UST / Tank Closure Paperwork by State

Every license, notice, closure form and trust fund that underground storage tank removal requires in Alabama, Louisiana, Mississippi and Florida.

Alabama

ADEM - Land Division, UST Compliance Program →
Who / what you need
Certified closure supervision
Permanent closure must be performed under the supervisory control of a certified individual (Ala. Admin. Code 335-6-15-.34). Official page →
Alabama Licensing Board for General Contractors
State GC license for commercial work over the board threshold - confirm your classification with the board. Official page →
Paperwork — in order
1. 30-day closure notice to ADEM
Written notice at least 30 days before permanent closure or change-in-service begins. Official page →
2. Closure site assessment (ADEM Form 474)
Excavation-zone assessment performed after notice, before closure is complete. Official page →
3. UST notification update (ADEM Form 279)
Amended UST notification recording the closure. Official page →
4. Notice of final closure
Submitted to ADEM upon completion, with tank/waste disposition records and manifests. Official page →
Alabama Underground & Aboveground Storage Tank Trust Fund (ATTF)
Official page →

Louisiana

LDEQ - Underground Storage Tank Division →
Who / what you need
LDEQ UST Certified Worker - Closure
Tank cleaning, purging/inerting, sampling, removal or fill-in-place must be done by/under an LDEQ-certified worker. Two certification types (Installations/Repairs and Closure); valid 2 years; 16 hrs continuing education to renew. Official page →
Louisiana State Licensing Board for Contractors
State contractor license with the appropriate hazardous-materials classification - confirm with LSLBC. Official page →
Paperwork — in order
1. 30-day Notice of Intent (UST-SURV-01)
Notification of Intent to Perform a Closure or Change-in-Service, to the LDEQ regional office 30 days ahead (waivable for extenuating circumstances). Official page →
2. 7-day scheduling notice (UST-ENF-05)
Phone/fax/email notice to the regional office 7 days before the closure date. Official page →
3. Closure Assessment (UST-SURV-02)
Owner + certified-worker signatures, scaled site drawing, lab results with QA/QC and chain-of-custody, manifests / bills of lading for tank, soil and fluids. Official page →
4. Closure report - 60 days
Closure assessment results due to LDEQ within 60 days of permanent closure. Official page →
Louisiana Motor Fuels UST Trust Fund
Official page →

Mississippi

MDEQ - Groundwater Assessment & Remediation Division, UST Branch →
Who / what you need
MDEQ Certified Contractor - Permanent Closure
An MDEQ-certified contractor MUST supervise permanent closure of any UST in use on/after Dec 22, 1988. Separate exams for Permanent Closure and Installation/Alteration (study: API 1604, 1615, 1632); testing in Jackson. Official page →
MS State Board of Contractors
Certificate of responsibility with the appropriate classification - confirm with the board. Official page →
Paperwork — in order
1. 30-day Notice of Intent to Permanently Close
Owner signature + certified contractor name required; notice lapses if closure does not start within 120 days. Official page →
2. UST notification update (MS NOTIFORM)
State UST notification form recording tank status. Official page →
3. Closure sampling + records
Soil/groundwater samples where contamination is most likely, analytical results, chain-of-custody, waste manifests, and a site drawing with tank/sample/piping locations. Official page →
4. Closure Report - 60 days
UST System Closure Report signed by owner AND certified contractor, due 60 days after completion. Official page →
Mississippi Groundwater Protection Trust Fund
Official page →

Florida

FDEP - Storage Tank Compliance (plus county-delegated programs) →
Who / what you need
Pollutant Storage Systems Contractor (PSSC)
DBPR/CILB license (FS 489.133) covering installation, maintenance, repair, alteration and removal of pollutant storage tanks. Requires 4 years experience (1 supervisory) and the Pearson VUE trade exam. Official page →
Paperwork — in order
1. Closure notice to FDEP / county program
Notify before closure - many Florida counties run delegated tank programs; follow the FDEP closure flowchart for your county. Official page →
2. Installation/Removal form - 62-761.900(5)
Certified-contractor form filed for UST removals (form rev. 7/9/2019, current as of 2026-08-30). Official page →
3. Closure Integrity Evaluation - 62-761.900(7)
UST closure integrity report, to the County with the closure notification 30-45 days before closure (AST: 62-762.901(7)). BidToolkit fills this one - see the Tank Closure Packet. Official page →
4. Limited Closure Report - 62-761.900(8)
UST limited closure report (AST: 62-762.901(8)); incident notification on 62-761.900(6) if contamination is found. Official page →
FDEP Petroleum Restoration Program / Inland Protection Trust Fund
Official page →
On every job, regardless of state:
✓ Certified worker / contractor credentials on site (state cert card)
✓ Signed notice-of-intent copy + agency acknowledgment
✓ Tank disposal receipts and waste manifests (soil, liquids, tank steel)
✓ Chain-of-custody forms for every sample sent to the lab
✓ Scaled site drawing: tanks, piping, dispensers, sample points + depths
✓ Photos: tanks in place, excavation, tank condition after removal
✓ Lab analytical package with QA/QC for the closure report
✓ EPA hazardous-waste manifest (only if soils/liquids test hazardous)
BidToolkit finds the bids and keeps the paperwork straight.
Nightly bid scans for Gulf Coast contractors, plus working guides like this one inside the app.
Start your 14-day free trial →
Every fact above was checked against the official agency or board page (last verified August 2026), and every link lands on the official source. This is a working guide, not legal advice — confirm requirements with the agency for your specific job. · All guides · bidtoolkit.com · brian@bidtoolkit.com