UST / Tank Closure Paperwork by State
Every license, notice, closure form and trust fund that underground storage tank removal requires in Alabama, Louisiana, Mississippi and Florida.
Alabama
ADEM - Land Division, UST Compliance Program →
Who / what you need
Certified closure supervision
Permanent closure must be performed under the supervisory control of a certified individual (Ala. Admin. Code 335-6-15-.34).
Official page →
Alabama Licensing Board for General Contractors
State GC license for commercial work over the board threshold - confirm your classification with the board.
Official page →
Paperwork — in order
1. 30-day closure notice to ADEM
Written notice at least 30 days before permanent closure or change-in-service begins.
Official page →
2. Closure site assessment (ADEM Form 474)
Excavation-zone assessment performed after notice, before closure is complete.
Official page →
3. UST notification update (ADEM Form 279)
4. Notice of final closure
Submitted to ADEM upon completion, with tank/waste disposition records and manifests.
Official page →
Alabama Underground & Aboveground Storage Tank Trust Fund (ATTF)
- Corrective-action work is reimbursed only through ADEM-approved Response Action Contractors - get on the approved list first.
- Cost proposals on ATTF Forms 031/032; submissions go through the AEPACS portal.
- February 2024 ATTF guidance document covers rates and reimbursement rules.
Official page →
Louisiana
LDEQ - Underground Storage Tank Division →
Who / what you need
LDEQ UST Certified Worker - Closure
Tank cleaning, purging/inerting, sampling, removal or fill-in-place must be done by/under an LDEQ-certified worker. Two certification types (Installations/Repairs and Closure); valid 2 years; 16 hrs continuing education to renew.
Official page →
Louisiana State Licensing Board for Contractors
State contractor license with the appropriate hazardous-materials classification - confirm with LSLBC.
Official page →
Paperwork — in order
1. 30-day Notice of Intent (UST-SURV-01)
Notification of Intent to Perform a Closure or Change-in-Service, to the LDEQ regional office 30 days ahead (waivable for extenuating circumstances).
Official page →
2. 7-day scheduling notice (UST-ENF-05)
Phone/fax/email notice to the regional office 7 days before the closure date.
Official page →
3. Closure Assessment (UST-SURV-02)
Owner + certified-worker signatures, scaled site drawing, lab results with QA/QC and chain-of-custody, manifests / bills of lading for tank, soil and fluids.
Official page →
4. Closure report - 60 days
Closure assessment results due to LDEQ within 60 days of permanent closure.
Official page →
Louisiana Motor Fuels UST Trust Fund
- Reimburses eligible site assessment and remediation on qualifying motor-fuel UST releases.
- January 2025 guidance document covers eligibility and claims; administered by LDEQ Financial Services.
Official page →
Mississippi
MDEQ - Groundwater Assessment & Remediation Division, UST Branch →
Who / what you need
MDEQ Certified Contractor - Permanent Closure
An MDEQ-certified contractor MUST supervise permanent closure of any UST in use on/after Dec 22, 1988. Separate exams for Permanent Closure and Installation/Alteration (study: API 1604, 1615, 1632); testing in Jackson.
Official page →
MS State Board of Contractors
Certificate of responsibility with the appropriate classification - confirm with the board.
Official page →
Paperwork — in order
1. 30-day Notice of Intent to Permanently Close
Owner signature + certified contractor name required; notice lapses if closure does not start within 120 days.
Official page →
2. UST notification update (MS NOTIFORM)
3. Closure sampling + records
Soil/groundwater samples where contamination is most likely, analytical results, chain-of-custody, waste manifests, and a site drawing with tank/sample/piping locations.
Official page →
4. Closure Report - 60 days
UST System Closure Report signed by owner AND certified contractor, due 60 days after completion.
Official page →
Mississippi Groundwater Protection Trust Fund
- Covers eligible cleanup up to $1.5M on qualifying motor-fuel UST releases - but NOT the tank removal itself.
- Work needs prior written MDEQ approval by an approved response action contractor to be reimbursable.
- Contractor invoices the owner; owner forwards to MDEQ for payment from the fund.
Official page →
Florida
FDEP - Storage Tank Compliance (plus county-delegated programs) →
Who / what you need
Pollutant Storage Systems Contractor (PSSC)
DBPR/CILB license (FS 489.133) covering installation, maintenance, repair, alteration and removal of pollutant storage tanks. Requires 4 years experience (1 supervisory) and the Pearson VUE trade exam.
Official page →
Paperwork — in order
1. Closure notice to FDEP / county program
Notify before closure - many Florida counties run delegated tank programs; follow the FDEP closure flowchart for your county.
Official page →
2. Installation/Removal form - 62-761.900(5)
Certified-contractor form filed for UST removals (form rev. 7/9/2019, current as of 2026-08-30).
Official page →
3. Closure Integrity Evaluation - 62-761.900(7)
UST closure integrity report, to the County with the closure notification 30-45 days before closure (AST: 62-762.901(7)). BidToolkit fills this one - see the Tank Closure Packet.
Official page →
4. Limited Closure Report - 62-761.900(8)
UST limited closure report (AST: 62-762.901(8)); incident notification on 62-761.900(6) if contamination is found.
Official page →
FDEP Petroleum Restoration Program / Inland Protection Trust Fund
- State-funded cleanup of eligible discharges through the Petroleum Restoration Program - contractors work through FDEP's procurement process for PRP sites.
Official page →
On every job, regardless of state:
✓ Certified worker / contractor credentials on site (state cert card)
✓ Signed notice-of-intent copy + agency acknowledgment
✓ Tank disposal receipts and waste manifests (soil, liquids, tank steel)
✓ Chain-of-custody forms for every sample sent to the lab
✓ Scaled site drawing: tanks, piping, dispensers, sample points + depths
✓ Photos: tanks in place, excavation, tank condition after removal
✓ Lab analytical package with QA/QC for the closure report
✓ EPA hazardous-waste manifest (only if soils/liquids test hazardous)