Construction Stormwater Permits by State
The NPDES/LPDES coverage, notices of intent and SWPPP plans that land disturbance of an acre or more requires in AL, LA, MS and FL.
Alabama
ADEM - NPDES Construction Stormwater Program →
Who / what you need
Construction General Permit ALR100000
Coverage required for land disturbance of one acre or greater - or under one acre when part of a common plan of development or sale of an acre or more. The 2026 CGP took effect April 1, 2026.
Official page →
Qualified Credentialed Professional (QCP)
The stormwater plan (CBMPP) must be prepared AND certified by a QCP - line that person up before the NOI goes in.
Official page →
Paperwork — in order
1. CBMPP - Construction Best Management Practices Plan
QCP-prepared and certified erosion/sediment control plan, implemented and maintained for the life of the job.
Official page →
2. Notice of Intent (NOI)
Submitted per the permit requirements before land disturbance begins.
Official page →
3. Inspection reports & BMP certification
ADEM publishes an NPDES Construction Stormwater Inspection Report and BMP Certification form - keep inspections current per your permit conditions.
Official page →
Key rules
- The 2026 Construction General Permit replaced the expired 2021 permit on April 1, 2026 - re-check conditions if your coverage predates it.
- MS4 cities and counties can add their own local stormwater requirements on top of ALR100000.
Official page →
Louisiana
LDEQ - Water Permits Division (LPDES) →
Who / what you need
LAR100000 - large construction (5+ acres)
LPDES general permit for stormwater discharges from construction disturbing 5 acres or more.
Official page →
LAR200000 - small construction (1-5 acres)
Covers disturbance of 1 up to 5 acres. Under 1 acre there is no LDEQ requirement (local rules can still apply).
Official page →
Paperwork — in order
1. SWPPP - before construction
Prepare the Storm Water Pollution Prevention Plan before work starts; keep it on site. Do NOT submit it to LDEQ - the permit is self-implementing, and the NOI certifies the SWPPP exists and complies.
Official page →
2. Notice of Intent (form CSW-G)
Select the number of coverage years (through final stabilization) and pay all annual fees with the NOI. Authorization comes 48 hours after the postmark of a complete NOI.
Official page →
3. Notice of Termination / transfer
An NOT must be submitted when an ongoing project transfers to a different operator.
Official page →
Key rules
- Formal written notification typically arrives 4-6 weeks after the NOI, but you may start 48 hours after a complete NOI is postmarked or hand-delivered.
- MS4 parishes and municipalities can add local requirements.
Official page →
Mississippi
MDEQ - Environmental Permits Division →
Who / what you need
Large Construction General Permit (5+ acres)
Coverage for disturbance of 5 acres and greater; NOI, recoverage and major-modification forms on the MDEQ page.
Official page →
Small Construction General Permit (1 to <5 acres)
Covers 1 up to 5 acres. Administratively continued past its April 30, 2024 expiration while MDEQ works toward reissuance - check the page for the current permit.
Official page →
Paperwork — in order
1. SWPPP per the MDEQ guidance manual
Stormwater Pollution Prevention Plan per the Mississippi SWPPP Guidance Manual, maintained through the job.
Official page →
2. Notice of Intent - electronic
Apply electronically through the MDEQ portal; your Certificate of Coverage prints from enSearch Online using the nine-digit coverage number.
Official page →
3. Request for Termination
Submit the termination form to end coverage when the site is stabilized.
Official page →
Key rules
- Large jobs needing continued coverage use the Recoverage Form; scope changes use the Major Modification Form.
- MS4 cities and counties can add local requirements.
Official page →
Florida
FDEP - NPDES Stormwater Program (Construction Activity) →
Who / what you need
Construction Generic Permit (62-621.300(4), F.A.C.)
Coverage required for construction disturbing one acre or more - or less than an acre when part of a common plan of development or sale. Coverage runs 5 years, then renew or terminate.
Official page →
Paperwork — in order
1. SWPPP - before the NOI
Develop the Stormwater Pollution Prevention Plan as part of permit compliance.
Official page →
2. Notice of Intent (form 62-621.300(4)(b))
Submit at least 2 calendar days before construction begins. Fees: $400 large construction (5+ acres), $250 small (1-5 acres).
Official page →
3. Notice of Termination
Submit the NOT within 14 calendar days after the site reaches final stabilization.
Official page →
Key rules
- Coverage lasts five years from issuance - renew or terminate at the end of the term.
- MS4 counties and cities can add local requirements on top of the generic permit.
Official page →
On every job, regardless of state:
✓ SWPPP / CBMPP on site, current, and matching what is actually built
✓ NOI acknowledgment / coverage number posted or in the job file
✓ Erosion & sediment BMPs installed BEFORE dirt moves
✓ Inspection logs kept per your permit (including after rain events)
✓ Plan updated whenever site conditions or phasing change
✓ Stabilization documented; termination notice filed when done
✓ Check the local MS4 city/county for stacked requirements
✓ Call 811 for utility locates before any excavation