BidToolkit
Site Work · AL · LA · MS · FL

Construction Stormwater Permits by State

The NPDES/LPDES coverage, notices of intent and SWPPP plans that land disturbance of an acre or more requires in AL, LA, MS and FL.

Alabama

ADEM - NPDES Construction Stormwater Program →
Who / what you need
Construction General Permit ALR100000
Coverage required for land disturbance of one acre or greater - or under one acre when part of a common plan of development or sale of an acre or more. The 2026 CGP took effect April 1, 2026. Official page →
Qualified Credentialed Professional (QCP)
The stormwater plan (CBMPP) must be prepared AND certified by a QCP - line that person up before the NOI goes in. Official page →
Paperwork — in order
1. CBMPP - Construction Best Management Practices Plan
QCP-prepared and certified erosion/sediment control plan, implemented and maintained for the life of the job. Official page →
2. Notice of Intent (NOI)
Submitted per the permit requirements before land disturbance begins. Official page →
3. Inspection reports & BMP certification
ADEM publishes an NPDES Construction Stormwater Inspection Report and BMP Certification form - keep inspections current per your permit conditions. Official page →
Key rules
Official page →

Louisiana

LDEQ - Water Permits Division (LPDES) →
Who / what you need
LAR100000 - large construction (5+ acres)
LPDES general permit for stormwater discharges from construction disturbing 5 acres or more. Official page →
LAR200000 - small construction (1-5 acres)
Covers disturbance of 1 up to 5 acres. Under 1 acre there is no LDEQ requirement (local rules can still apply). Official page →
Paperwork — in order
1. SWPPP - before construction
Prepare the Storm Water Pollution Prevention Plan before work starts; keep it on site. Do NOT submit it to LDEQ - the permit is self-implementing, and the NOI certifies the SWPPP exists and complies. Official page →
2. Notice of Intent (form CSW-G)
Select the number of coverage years (through final stabilization) and pay all annual fees with the NOI. Authorization comes 48 hours after the postmark of a complete NOI. Official page →
3. Notice of Termination / transfer
An NOT must be submitted when an ongoing project transfers to a different operator. Official page →
Key rules
Official page →

Mississippi

MDEQ - Environmental Permits Division →
Who / what you need
Large Construction General Permit (5+ acres)
Coverage for disturbance of 5 acres and greater; NOI, recoverage and major-modification forms on the MDEQ page. Official page →
Small Construction General Permit (1 to <5 acres)
Covers 1 up to 5 acres. Administratively continued past its April 30, 2024 expiration while MDEQ works toward reissuance - check the page for the current permit. Official page →
Paperwork — in order
1. SWPPP per the MDEQ guidance manual
Stormwater Pollution Prevention Plan per the Mississippi SWPPP Guidance Manual, maintained through the job. Official page →
2. Notice of Intent - electronic
Apply electronically through the MDEQ portal; your Certificate of Coverage prints from enSearch Online using the nine-digit coverage number. Official page →
3. Request for Termination
Submit the termination form to end coverage when the site is stabilized. Official page →
Key rules
Official page →

Florida

FDEP - NPDES Stormwater Program (Construction Activity) →
Who / what you need
Construction Generic Permit (62-621.300(4), F.A.C.)
Coverage required for construction disturbing one acre or more - or less than an acre when part of a common plan of development or sale. Coverage runs 5 years, then renew or terminate. Official page →
Paperwork — in order
1. SWPPP - before the NOI
Develop the Stormwater Pollution Prevention Plan as part of permit compliance. Official page →
2. Notice of Intent (form 62-621.300(4)(b))
Submit at least 2 calendar days before construction begins. Fees: $400 large construction (5+ acres), $250 small (1-5 acres). Official page →
3. Notice of Termination
Submit the NOT within 14 calendar days after the site reaches final stabilization. Official page →
Key rules
Official page →
On every job, regardless of state:
✓ SWPPP / CBMPP on site, current, and matching what is actually built
✓ NOI acknowledgment / coverage number posted or in the job file
✓ Erosion & sediment BMPs installed BEFORE dirt moves
✓ Inspection logs kept per your permit (including after rain events)
✓ Plan updated whenever site conditions or phasing change
✓ Stabilization documented; termination notice filed when done
✓ Check the local MS4 city/county for stacked requirements
✓ Call 811 for utility locates before any excavation
BidToolkit finds the bids and keeps the paperwork straight.
Nightly bid scans for Gulf Coast contractors, plus working guides like this one inside the app.
Start your 14-day free trial →
Every fact above was checked against the official agency or board page (last verified August 2026), and every link lands on the official source. This is a working guide, not legal advice — confirm requirements with the agency for your specific job. · All guides · bidtoolkit.com · brian@bidtoolkit.com